Production Capacity & Takt Time Calculator

Compare customer demand with available production time.

The interactive calculator loads above this explanation when JavaScript is available.

How to use the production capacity & takt time calculator

Compare customer demand with available production time. Enter the known values, choose units where offered, and read the live result and breakdown.

Worked example

This example uses the following inputs. Currency amounts are illustrated in USD.

Shift duration
8 h
Breaks per shift
30 min
Changeovers per shift
20 min
Number of shifts
1
Required good units
400
Cycle time per unit
55 s
Good-unit yield
98 %
Parallel identical machines
1

Customer takt time: 64.5 s/unit

Method

Takt = net scheduled time / demand. Capacity = completed cycles × parallel machines × yield. Assumes identical independent machines, no other bottleneck or downtime; cycle time and customer takt are different measures.

What to watch for

Uses your supplied dimensions and assumptions. Check product specifications before purchasing or operating equipment.

Assumptions and references

Uses your supplied dimensions and assumptions. Check product specifications before purchasing or operating equipment.

Formula implementation: v0.8.0. Examples are checked against the calculation engine; specialist professional review is not claimed. How we check calculations.

Report a problem with this calculator

Related calculators