How to use the production capacity & takt time calculator
Compare customer demand with available production time. Enter the known values, choose units where offered, and read the live result and breakdown.
Worked example
This example uses the following inputs. Currency amounts are illustrated in USD.
- Shift duration
- 8 h
- Breaks per shift
- 30 min
- Changeovers per shift
- 20 min
- Number of shifts
- 1
- Required good units
- 400
- Cycle time per unit
- 55 s
- Good-unit yield
- 98 %
- Parallel identical machines
- 1
Customer takt time: 64.5 s/unit
Method
Takt = net scheduled time / demand. Capacity = completed cycles × parallel machines × yield. Assumes identical independent machines, no other bottleneck or downtime; cycle time and customer takt are different measures.
What to watch for
Uses your supplied dimensions and assumptions. Check product specifications before purchasing or operating equipment.
Assumptions and references
Uses your supplied dimensions and assumptions. Check product specifications before purchasing or operating equipment.
Formula implementation: v0.8.0. Examples are checked against the calculation engine; specialist professional review is not claimed. How we check calculations.